Planning Permit
Verified 20 September 2024 - Directorate for Legal and Administrative Information (Prime Minister)
You want to set up a housing estate, a campsite, a parking area, a sports field or a leisure area or a reception area for travelers (AAGV: titleContent) or do earthwork?. Before starting your work, you must obtain a planning permit (PA). It's issued by the city hall. We guide you through the steps of applying for a permit.
Step-by-step approach
You must first inquire with your city hall to find out if your project is in a protected area, because the rules are different.
Protected sites are remarkable heritage sites, the historic landmarks, the classified or pending sites, nature reserves, the heart of national parks or a future national park.
General case
The improvements and works subject to development permits are as follows:
Protected area
The improvements and works subject to development permits are as follows:
The application for authorization may be made by natural and moral following:
- Owner(s) of the land or its representative
- Purchaser of the property
- Company authorized by the owner(s) to carry out the work
- No one in division or his representative
- Trustee and co-owner
- Beneficiary of expropriation (public service, public establishment, chamber of commerce...).
The way to build your planning permit file differs depending on whether you are in Paris or in another municipality:
General case
You have to fill in your permit file by paperless means according to the arrangements made by your municipality or on a paper form. Inquire on the website of the city hall or on site.
Who shall I contact
On the Internet
You can complete your planning permit application on the Internet:
In Paris
You must submit your file to the Office Accueil et service à l'user (Basu: titleContent) by dematerialized means only:
Office Accueil et Service à l'User (Basu) de Paris: one-stop-shop
Depending on whether you are in Paris or another municipality, you must file your application:
- By dematerialized according to the arrangements made by your municipality (inquire on the site of the town hall or on the spot)
- By letter RAR: titleContent
- In your own hand.
General case
Via the Internet
You can send your PNR application file via the Internet:
Support for your city planning authorization request
When you send your request by hand or by post, the City Hall will issue you a receipt. When you submit your application electronically, the receipt shall consist of the electronic acknowledgement of receipt.
The receipt contains the registration number of your file and the information allowing you to know the date from which the work can start.
He states that, within 1 month of the filing of the file, the City Hall can notify a different time frame to start your work. She also has 1 month to notify you if your file is incomplete.
Filing in town hall or by mail
Your permit application can be submitted or mailed RAR: titleContent to the town hall.
You must deposit 4 complete files in town hall.
In some cases, additional copies you are asked to:
- Project located within the perimeter of a remarkable heritage site, to historic landmarks, in a classified site, registered site or in a nature reserve: 1 additional copy
- Project located in a national park core: 2 additional copies
- Project subject to commercial authorization: 2 additional copies (1 of which is in dematerialized form).
You must attach 5 copies of the situational plan and the overall compositional plan.
In the case of a construction, you must also provide 5 copies of ground plane, the plan of the facades and roofs and the sectional plane.
If the operation is located on 2 communes, the file is preferably lodged in the municipality where the project is mainly located.
In Paris
You must submit your file to the Office Accueil et service à l'user (Basu: titleContent) by dematerialized means only:
Office Accueil et Service à l'User (Basu) de Paris: one-stop-shop
The city hall delivers you a receipt following the filing of your file.
The receipt contains the registration number and information allowing you to know the date from which the work can start.
This date differs depending on whether your file is complete or not:
Complete file
The response time is usually 3 months from the date of submission of the application.
The City Hall must notify you within one month of the date of filing your permit file if the investigation period is longer. This is the case for:
- Project located within the perimeter of a remarkable heritage site or to historic landmarks : 4 months
- Draft submitted for the opinion of the Departmental Commission for the Preservation of Natural, Agricultural and Forestry Areas: 4 months
- Project subject to commercial exploitation authorization: 5 months
- Project located in an area intended to be classified in the heart of a future national park or in the heart of a defined national park: 5 months.
Incomplete Folder
City Hall has 1 month to notify you that your file is incomplete. You must complete it within 3 months. If you do not provide the missing documents, your application will be considered rejected.
The instruction timeout starts when your folder is full.
The response time is usually 3 months from the date of submission of the application.
The City Hall must notify you within one month of the date of filing your permit file if the investigation period is longer. This is the case for:
- Project located within the perimeter of a remarkable heritage site or to historic landmarks : 4 months
- Draft submitted for the opinion of the Departmental Commission for the Preservation of Natural, Agricultural and Forestry Areas: 4 months
- Project subject to commercial exploitation authorization: 5 months
- Project located in an area intended to be classified in the heart of a future national park or in the heart of a defined national park: 5 months.
The decision is addressed to you by letter RAR: titleContent or by READ: titleContent or an equivalent electronic process.
You may receive a decision authorizing, refusing, staying the proceedings or not receive a reply:
Répondez aux questions successives et les réponses s’afficheront automatiquement
Authorization
The city council's decision takes the form of a decree. It may be accompanied by requirements particulars for which the administration must give reasons.
Warning
The City Hall may withdraw a permit if it considers that it has been illegally issued within 3 months of the date of authorization of the development permit.
Refusal
The refusal of development permits takes the form of a decree which specifies all the grounds for refusal of the administration. It shall also indicate the ways and time limits for appeal.
Stay of proceedings
In certain circumstances, the mayor can defer his decision on your license for up to 2 years. This is the case, for example, when your work request may compromise or make more expensive the execution of a future local city planning plan (MORE: titleContent) or a development operation.
The mayor takes a decree stay of proceedings which indicates the duration of the period.
Your application is neither accepted nor refused. It will be considered later.
The stay of proceedings may concern any application for authorization concerning works, constructions or installations in the following cases:
- Land which forms part of the perimeter of a concerted development area (Zac: titleContent)
- Initiation of the investigation prior to the declaration of public interest (DUP: titleContent) of an operation
- Planned constructions which may jeopardize or make more expensive the execution of public works or the carrying out of a development operation
- Planned constructions likely to jeopardize or make more expensive the execution of the future MORE: titleContent
- Project located in an area intended to be in the heart of a national park.
Reasons for the decision and time-limits for appeal are specified in the order.
Within 2 months of the expiry of the stay of proceedings, you must confirm your permit application.
Within 2 months of your request, you will receive the mayor's decision. If you do not receive the mayor's decision within this period, your permit is considered granted.
FYI
Landowners who have been ordered to stay the proceedings may demand that the community (or the public service that has taken the initiative) purchase their land. The community has 1 year to comment.
Lack of response
In principle, if you do not receive a reply from the City Hall at the end of the investigation period, the license is tacitly tuned. On simple written request from you, the city hall can issue you a license certificate.
Warning
Within 3 months of the date of the permit decision, the City Hall may withdraw the permit if it considers that it was issued illegally.
However, failure to respond by the administration is rejection unspoken permits in the following cases:
- Draft submitted for opinion to the departmental commission for commercial development
- Project to extend or reopen a cinema whose application has been refused by the competent departmental committee
- Work subject to authorization by the Minister of Defense.
You can make a appeal to the administrative court within 2 months of decision unspoken rejection.
Who shall I contact
Display Object and Duration
L'display of development permit on the ground east obligatory. Where a permit is obtained unspokenNo, it's the license certificate which must be displayed. You have to ask the city council beforehand.
You must display this view on notification of the order or as soon as the time limit for the investigation of your file is completed (in case of a permit unspoken).
It must remain in place for the duration of the work.
An extract of the permit is displayed in the town hall within 8 days of the issuance of the authorization and for 2 months.
View shape and content
You must use a rectangular panel with dimensions greater than 80 cm. It must be visible from the outside. The information on your billboard must be legible on the public highway or in spaces open to the public.
The display shows the following information:
- Beneficiary's name, business name or trade name
- Date and number of permit
- Nature of the project, land area
- Address of the town hall where the file can be consulted
- Name of thearchitect author of the architectural project.
It shall also indicate, depending on the nature of the project, the following:
- Floor area authorized and the height of the building(s), expressed in meters in relation to the natural ground, if the project involves building(s)
- Maximum number of lots expected if the project is on a subdivision
- Total number of pitches and, if applicable, the number of pitches reserved for light recreational dwellings if the project involves a campground or a residential recreational park
- Area of building(s) to be demolished if the project involves demolitions.
The display shall also mention the possibility for third party to exercise a appeal. They must then notify the licensee within 15 days of their appeal. For 2 months from 1er field display day, such third parties may in fact carry out a ex gratia appeal to the mayor who issued the authorization.
In the absence of a notice, they will be able to contest the authorization for 6 months after the completion of the work.
When the mayor refuses your application for a development permit or takes a decree you can challenge it.
In the 2 months that follow the date of notification from the decision or from the date on which an implied decision of rejection arose, you can make a ex gratia appeal by letter RAR: titleContent by the town hall.
Who shall I contact
If your grace attempt fails, you have a new grace period of 2 months to make aappeal to the administrative court, by letter RAR: titleContent. You must clearly state the reasons for your right to a planning permit.
You must apply to the administrative court on which the municipality where your project is located depends.
Who shall I contact
Please note
You can also to bring proceedings before the administrative court within 2 months of the date of notification of the decision to refuse the permit, without making an ex gratia appeal.
The development permit has a period of validity which can be extended on request.
Period of validity of the development permit
The development permit has a period of validity of 3 years. It expires if you have not started the work within 3 years or if, after this period, you interrupt it for more than 1 consecutive year.
Apply for an extension of the development permit
The period of validity may be extended 2 times for 1 year if the city planning rules and administrative easements have not changed.
You have to do it demand at least 2 months before the initial period of validity of your city planning authorization (or before the end of the validity period of your 1re request for extension).
This request must be made in 2 copies by letter RAR: titleContent or dropped off in town hall.
Upon receipt of your request, the City Hall has 2 months to answer you.
The extension is granted if you do not receive a reply within this time limit.
Only the valid city planning permissions may be prolonged.
Example :
An authorization valid from June 5, 2024 to June 5, 2027 can be extended for 1 year if you apply before April 5, 2027.
It can be extended to a 2e times if you request it 2 months before the end of the 1re extension granted.
The site opening declaration is mandatory.
General case
Before you begin your work, you must declare the opening of the site on a form to be deposited or sent to the town hall, preferably by letter RAR: titleContent :
In Paris
Before you begin your work, you must declare the opening of the construction site at the Basu only by dematerialized means:
Office Accueil et Service à l'User (Basu) de Paris: one-stop-shop
When you have finished your work, you must send to the town hall, or to the Basu: titleContent for Paris, a declaration of completion and conformity of works (DAACT: titleContent) of your work.
You have to pay various contributions: a tax, a royalty and participations.
Tax, royalties and participations payable
The order informs you of the amount of any contributions you have to pay. They may include the following:
- Development tax
- Preventive Archeology Fee
- EAP: titleContent
- Participation for the construction of public parking lots or PNRAS: titleContent
- Pepe: titleContent
- PVR: titleContent
- Participation of local residents (in the departments of Bas-Rhin, Haut-Rhin and Moselle).
Equity may also take the form of:
- Execution of works: the decree specifies the general characteristics of the works and the estimated cost
- Contributions of built or unbuilt land: the decree indicates the area to be transferred and the value of the land.
Please note
The connection to the sewer of new or existing constructions generates the payment of the contribution for the financing of the collective sanitation (Pfac: titleContent or Pac).
Know the amounts and pay
You should contact your property tax center for the development tax and the preventive archeology charge :
You must contact the city planning department of your town hall for the holdings :
Who shall I contact
Support for your city planning authorization request
Office Accueil et Service à l'User (Basu) de Paris: one-stop-shop
Who can help me?
Find who can answer your questions in your region
For information on city planning regulations and administrative procedures
Telephone administrative information - Allo Public Service
For more information on this topic, you can contact Allô Service Public.
Attention: the service does not have access to users' personal files and cannot therefore provide information on their status.
- Lundi : de 08h30 à 17h30
- Mardi : de 08h30 à 12h15
- Mercredi : de 08h30 à 12h15
- Jeudi : de 08h30 à 17h30
- Vendredi : de 13h00 à 16h15
- Service free
The informants who answer you belong to the ministry in charge of housing and city planning.
For information on the local city planning plan, your development permit file or on participations
Town HallFor information on the local city planning plan or your planning permit file in Paris
Paris: Reception and service desk (Basu)For information on the development tax and the preventative archeology fee
Departmental Property Tax Center (CDIF)
Decisions of the City Hall
Display of development permit
Use of an architect or landscape designer for subdivisions
Tax, royalties and participations
Work requiring a development permit
Application for city planning authorization: holders of the right of deposit and number of copies
Deadline for instruction for a development permit
Declaration of the opening of the construction site
Period of validity of the city planning authorization
Time-limit for taking evidence under ordinary law
Instruction time increased
Use of an architect or landscape designer for subdivisions
Declaration of Completion and Conformity of Work (ACCED)